Better Late then Never – Rail Drop Table Assembly in India

Bangalore, India, March 2016

The Tender for this project was bid in late 2009 for a Whiting 50 ton drop table with two service tops and one bascule top for SWR (South Western Railways) in their Bangalore Facility.

Whiting officially won the order in late 2010, and it wasn’t until early 2012 that the SWR agreed on the Letter of Credit for payment.

Handling Specialty took the order to manufacture the equipment via Whiting in 2012 and shipped the product in mid-2013.

South West Railways did not complete construction on their pit to house the new drop table and bascule top equipment until early 2015.

When the pit was completed, one Whiting and one Handling Specialty technician were sent to Bangalore to oversee the installation and commissioning in Feb/March of 2016.

Flowers and food were brought in along with an Indian Holy man in a “blessing ritual,” which was performed once the units were installed.

Whiting and Handling Specialty have another drop table in operation in Ahmedabad, India, installed in 2014, and another in Hubli, from 2002, which is still performing well for our client.

Interested in Rail Products? Contact Rick Breznik

Recent News

Ben D'Souza - Handling Specialty President
CHCH pic
AREMA
Handling Specialty and AREMA
Ice Cream Trucks at Handling Specialty
Farnborough

We Build Big Things to Help Our Customers Build Big Things.

Contact us today to schedule a consultation.